PUBLIC STATEMENT
Several states remain opposed to
rewriting of geography through interlinking of rivers
After Supreme Court, Government
reveals there is no consensus on the mega project
Court observed NCAER Study “did not
consider the plan's environmental aspects or cost-benefit calculus”
ILR project & Ganga Waterway project
pose threat to Ganga basin, contrary to efforts for Ganga rejuvenation
April 17,
2015: The
terms of reference of the newly constituted ‘Task Force’ on Interlinking of
Rivers’ chaired by B N Navalawala reveals that Hon’ble Supreme Court’s order
dated February 27, 2012 in petitioner-less Writ Petition (Civil) No. 512 of
2002 is based on a flawed assumption that there is consensus and unanimity
among the states in the matter of Interlinking of Rivers concept/project. The attached
release of the Union Ministry of Water Resources, River Development & Ganga
Rejuvenation issued by Press Information Bureau states that the Task Force
“would also device suitable mechanisms for bringing about speedy consensus
amongst the states and also propose suitable organizational structure for
implementing the Interlinking of Rivers. The Task Force would also try to forge
a consensus amongst the states in order to take forward the speedy
implementation of the Interlinking of Rivers Program.”
The
terms of reference of the earlier Task Force on Inter-Linking of Rivers under
the Chairmanship of Suresh P. Prabhu that was constituted on December 13, 2002 was
also tasked to “Devise suitable mechanism for bringing about speedy consensus
amongst the States” revealing absence of unanimity on the implementation of ILR
project. (Photo:B.N. Navalawala, Former Secretary, Union Ministry of Water Resources)
The judgment in the petitioner-less
“Networking of Rivers" case inconsistently admitted absence of consensus
and unanimity among the states in the matter of Interlinking of Rivers concept/project
and still erroneously went on to conclude that there is unanimity and consensus.
Judgment dated February
27, 2012 in the “Networking of Rivers” case was authored by Justice Swatanter
Kumar on merits rigorous scrutiny because it seems to establish a disturbing
precedent by assuming “consensus” and “unanimity” although 18 States chose not
respond to the notice of Supreme Court of India “despite the grant of repeated
opportunities to do so.”
In such a scenario the
supreme question is why did the Supreme Court interfere in the policy matters
of the government against its own interpretation of its lakshman rekha and presume consensus among states, which is
manifestly non-existent as is evident from the Terms of Reference (TOR) of the
Task Force, constituted to ensure networking of rivers and also from the courts
most recent order. The TOR said, “Devise suitable mechanism for bringing about
a speedy consensus”. This presumed consensus is the ratio decidendi (the reasoning behind the decision) of the judgment
on networking of rivers. If something is a legal system, it must meet factual
criteria. In the case of the 'networking of rivers' one fails to come across a
cogent ratio decidendi that is “Any
rule of law expressly or impliedly treated by the judge as a necessary step in
reaching his conclusion.”
In a stark admission of
fact about the status of consensus among states in the matter of the project,
in para 26, the judgment reads: “The process of consensus building is on-going,
in regard to the feasibility of implementing other interlinking projects.” This
reveals that after almost 10 years of assumption of consensus does not have any
basis.
Para 20 of February
2012 judgment reads: “With regard to the approvals required, it is submitted
that the Ministry of Environment and Forests, Union of India had given some
clearances, while refusing the same in other cases. The consent of some of the
States had not been received. The expected financial implication as far back as
in 2002 was Rs.5, 60, 000 crores.” The source of financial estimate was never
disclosed. It has now come to light that it is a flawed estimate.
Although para 22 records that “The Union of India and some states have shown their concerns and their apprehensions about these projects, including questioning the reliability of water supply from distant sources, distribution of water given the existing tribunal awards and the continued availability of existing water surpluses”, the judgment does not throw any light on how these concerns have been responded to.
Although para 22 records that “The Union of India and some states have shown their concerns and their apprehensions about these projects, including questioning the reliability of water supply from distant sources, distribution of water given the existing tribunal awards and the continued availability of existing water surpluses”, the judgment does not throw any light on how these concerns have been responded to.
Para 24 of the judgment
reveals that “The last of the affidavits filed on behalf of the Union of India
was in December, 2003. This affidavit gives details of the States, with which a
dialogue was to be held as also the details of constitution of sub-committees.
The Terms of Reference of the Task Force included the approval of all links.
With the intention to arrive at a general consensus, before entering into
agreements, the Union of India has discussed details with Maharashtra and
Gujarat and preliminary discussion has taken place with the States of Andhra
Pradesh, Chattisgarh, Karnataka, Orissa, Tamil Nadu and Pondicherry.” This
shows that the assumption of consensus was/is premature.
The fact is that the
court has been misled into assuming that “there is unanimity of views among
all”. At para 28, the order records: “even comprehensive clearances, from the
Uttar Pradesh Government, have not been received. The State of Rajasthan
refuses to consider the MoU for another priority link,
Parbati-Kalisindh-Chambal, until the updation of its hydrology project.”
Para 27 of the judgment states: “In the Himalayan region, (Feasibility Reports) FRs of two remaining links were completed, i.e., the Sarda-Yamuna link and Ghagra-Yamuna Link. The field survey and investigation for Sone Dam on the southern tributaries of the Ganga link, was still in progress.” It adds, “The Ministry of Environment and Forests had refused permission for survey and investigation of the Manas-Sankosh-Tista-Ganga link, but the toposheet study for the alternative Jogigopa-Tista-Farakka link has been completed.”
Para 27 of the judgment states: “In the Himalayan region, (Feasibility Reports) FRs of two remaining links were completed, i.e., the Sarda-Yamuna link and Ghagra-Yamuna Link. The field survey and investigation for Sone Dam on the southern tributaries of the Ganga link, was still in progress.” It adds, “The Ministry of Environment and Forests had refused permission for survey and investigation of the Manas-Sankosh-Tista-Ganga link, but the toposheet study for the alternative Jogigopa-Tista-Farakka link has been completed.”
In the Peninsular
region, the projects relating to Bedti-Varada and Netravati-Hemavati-Tapi are
awaiting Karnataka Government's consent. In Netravati-Hemvati-Tapi link, the
Karnataka Government has refused to consent even to the preparation of FR until
decision of related cases, pending in the Courts.
Para 29 of the judgment
records: “In the Par-Tapi-Narmada and Damanganga-Pinjal links, residents have
shown concern about the extent of land to be submerged on the construction of
the proposed dam.”
Para 47 of judgment
reads: “…it is clear that primarily there is unanimity between all concerned
authorities including the Centre and a majority of the State Governments, with
the exception of one or two, that implementation of river linking will be very
beneficial. In fact, the expert opinions convincingly dispel all other
impressions.” The fact is contrary to the assertion about unanimity and facts
stated in the judgment itself demonstrate it.
It is noted in para 48
that “The States of Rajasthan, Gujarat, Tamil Nadu have fully supported the
concept.’
The real reason for
their support is that these are states which have exhausted their local water
resources. What is required is to examine the unsustainable uses that led to
these states becoming water stressed and rejuvenating their local sources
instead of inter-basin transfer. What is stated in para 50 is not true because
there is no unanimity in accepting interlinking of rivers and do not fall
within the domain of general consensus.
Para 52 of the judgment
seems to violate the federal spirit of the constitution wherein interest of the
individual States is sought to be sacrificed in the name of national interest.
South Asia’s biggest ecological crisis due to construction of embankments
happened in the name of national interest. Siberian rivers that were diverted
in former USSR which led to the world biggest ecological catastrophe, drying up
of Aral Sea also happened by invoking the cause of national interest.
Paragraph 14 of the judgment reads: “this Court, vide Order dated 31st October, 2002, recorded that there is in-principle consensus amongst all States to go ahead with the project of interlinking of rivers.” If one read the recent judgment of February 27, 2012 and the original order of October 31, 2002 together, it is quite manifest that both them are based on the assumption of “consensus” and “unanimity” among the States. This appears to be against ‘the principles of Federalism’ and ‘a Constitutional impropriety because the judgment itself notes that several states are opposed to it and some 18 states did not even respond to court’s repeated notices. A larger bench or legislature may have to set the factual position right in near future.
Paragraph 14 of the judgment reads: “this Court, vide Order dated 31st October, 2002, recorded that there is in-principle consensus amongst all States to go ahead with the project of interlinking of rivers.” If one read the recent judgment of February 27, 2012 and the original order of October 31, 2002 together, it is quite manifest that both them are based on the assumption of “consensus” and “unanimity” among the States. This appears to be against ‘the principles of Federalism’ and ‘a Constitutional impropriety because the judgment itself notes that several states are opposed to it and some 18 states did not even respond to court’s repeated notices. A larger bench or legislature may have to set the factual position right in near future.
Till February 2012,
only ten States responded to the court’s notices. In October 2002 when only one
State had filed the affidavit giving its consent even then the Court had
assumed consensus. The dictionary meaning of 'consensus' must be crying in its
grave. Out of these ten, the judgment records that “The States of Assam, Sikkim
and Kerala had raised their protests on the grounds that they should have exclusive
right to use their water resources and that such transfer should not affect any
rights of these States. The State of Sikkim was concerned with particular
reference to tapping of the hydro power potential in the State and the State of
Kerala entirely objected to long distance, inter-basin, water transfer.” The
assertion that Punjab has given their approval to the concept in-principle is
ambiguous because “according to the State of Punjab, inter-linking of rivers
should be started only from water-surplus States to States facing water
deficit.” Such contention is insincere given the fact that like Kerala
Assembly, Punjab Assembly too has unanimously opposed the proposal of
interlinking rivers. The former in the case of central plan and the latter in the
case of Sutlej-Yamuna link canal despite Supreme Court’s order as it remains
opposed to transfer water to Rajasthan. In the former case, Chief Minister of
Kerala, Oommen Chandy stated that the Supreme Court judgement on interlinking
of rivers would not apply to Kerala or its rivers on February 28, 2012 adding
that the verdict was applicable only to concurring States. “Kerala has opposed
interlinking of rivers. In view that, the judgement will not apply to us.” VS
Achuthanandan, Leader of Opposition in Kerala Assembly reacted, the project was
"detrimental" to the state's interests and termed as
"unfortunate" the Supreme Court directive to the Centre to implement
it.
Yamuna
Pollution case became Networking of Rivers case
On 16th September 2002
the Intervention Application No. 27 in the writ petition (civil) No. 725/1994
came up for hearing before the three-judge bench of the then Chief Justice,
Justice B.N. Kripal, Justice K.G Balakrishnan, and Justice Arijit Pasayat. Upon
hearing the counsel the court passed the order.
Paragraph 3 of the
February 2012 judgment reads: “We must notice, to put the records straight,
that on 29th September, 1994, a Bench of this Court took suo motu notice of a
write-up that had appeared in the Hindustan Times newspaper, dated 18th July,
1994, titled "And quiet flows the maili Yamuna".…Since then, the writ
petition is being continuously monitored by this Court, till date. During the
pendency of this writ petition, I.A. No. 27 came to be filed (which)…referred
to the address of Dr. A.P.J. Abdul Kalam, the then President of India, on the
eve of the Independence Day.” Para 4 of the judgment states, “This is how I.A.
No. 27 in Writ Petition (Civil) No. 725 of 1994 was converted into Writ
Petition (Civil) No. 512 of 2002. The Writ Petition (Civil) No. 512 of 2002 was
taken up for hearing and notice was issued to all the States, inviting
affidavits regarding their stance on the issue of networking of rivers.
It further reads: On
16th September, 2002, this Court, while considering the said I.A., directed
that the application be treated as an independent writ petition and issued
notice to the various State Governments as well as the Attorney General for
India and passed the following order:-"Based on the speech of the
President on the Independence Day Eve relating to the need of networking of the
rivers because of the paradoxical phenomenon of flood in one part of the
country while some other parts face drought at the same time, the present
application is filed. It will be more appropriate to treat to treat it as
independent Public Interest Litigation with the cause title "IN RE:
NETWORKING OF RIVERS -- v. ---" Amended cause title be filed within a
week. Issue notice returnable on 30th September, 2002 to the respondents as
well as to the Attorney General. Serve notice on the standing counsel of the
respective States.”
In para 7 of the order of 2012, it is stated that “we make it clear that presently, we are not dealing with Writ Petition (C) No. 725 of 1994.” It appears to be a glaring omission given the fact that the issue of quality of water which is the subject matter of original Writ Petition (C) No. 725 of 1994 is co-exists and is co-terminus with the quantity of water is the subject matter of I.A. No. 27 in it which was converted into Writ Petition (Civil) No. 512 of 2002. In fact I.A. No. 27 had advanced the prayer that networking of rivers will lead to dilution of pollution of polluted rivers.
Para 8 of February 2012 judgment states, “the National Water Policy which is being (is) updated on a yearly basis”, this is factually incorrect. The National Water Policy 2002 is now being updated in 2012 it was not updated in between. There is inter-basin transfer of water through interlining of rivers finds mention in both. It seems the whole Interlinking Project is a gimmick with no seriousness in it. It is only aimed at diverting the attention of the people from the issues facing them. Now for all the problems like irrigation, floods, waterlogging, rehabilitation, the conflicts of this side and that side, lower and upper riparians, malfunctioning of the projects, non-implementation of the promises, costs and so on, it is "Surf Excel Hai Naa" type of solution.
Referring to National Water Policy 2002, it further states, “The National Water Policy seeks to make available water supply to those areas which face shortages. This aspect of the matter could be effectively dealt with, only if the various rivers in the country are linked and are nationalized.” This is also not true because there are alternative and better cost effective ways of dealing with water supply shortages and the remedy for effectively dealing with it does not lie in linking various rivers in the country and nationalizing them. It is indeed shocking that the court was not informed about the alternative ways to deal with water supply shortages.
Para 9 of the order reveals that a National Perspective Plan (NPP) for optimum utilization of water resources in the country which envisaged inter-basin transfer of water from water-surplus to water-deficit areas was formulated in 1980, the pre-climate crisis period.
In para 7 of the order of 2012, it is stated that “we make it clear that presently, we are not dealing with Writ Petition (C) No. 725 of 1994.” It appears to be a glaring omission given the fact that the issue of quality of water which is the subject matter of original Writ Petition (C) No. 725 of 1994 is co-exists and is co-terminus with the quantity of water is the subject matter of I.A. No. 27 in it which was converted into Writ Petition (Civil) No. 512 of 2002. In fact I.A. No. 27 had advanced the prayer that networking of rivers will lead to dilution of pollution of polluted rivers.
Para 8 of February 2012 judgment states, “the National Water Policy which is being (is) updated on a yearly basis”, this is factually incorrect. The National Water Policy 2002 is now being updated in 2012 it was not updated in between. There is inter-basin transfer of water through interlining of rivers finds mention in both. It seems the whole Interlinking Project is a gimmick with no seriousness in it. It is only aimed at diverting the attention of the people from the issues facing them. Now for all the problems like irrigation, floods, waterlogging, rehabilitation, the conflicts of this side and that side, lower and upper riparians, malfunctioning of the projects, non-implementation of the promises, costs and so on, it is "Surf Excel Hai Naa" type of solution.
Referring to National Water Policy 2002, it further states, “The National Water Policy seeks to make available water supply to those areas which face shortages. This aspect of the matter could be effectively dealt with, only if the various rivers in the country are linked and are nationalized.” This is also not true because there are alternative and better cost effective ways of dealing with water supply shortages and the remedy for effectively dealing with it does not lie in linking various rivers in the country and nationalizing them. It is indeed shocking that the court was not informed about the alternative ways to deal with water supply shortages.
Para 9 of the order reveals that a National Perspective Plan (NPP) for optimum utilization of water resources in the country which envisaged inter-basin transfer of water from water-surplus to water-deficit areas was formulated in 1980, the pre-climate crisis period.
The contention in the
judgment that “Apart from diverting water from rivers which are surplus, to
deficit areas, the river linking plan in its ultimate stage of development will
also enable flood moderation” is flawed. There isn’t any credible piece of paper
that can support this claim.
The judgment acknowledges that “the construction of storage reservoirs on the principal tributaries of rivers Ganga and Brahmaputra in India, Bhutan and Nepal” makes it an international issue. Bangladesh is also an affected party as downstream country.
The judgment acknowledges that “the construction of storage reservoirs on the principal tributaries of rivers Ganga and Brahmaputra in India, Bhutan and Nepal” makes it an international issue. Bangladesh is also an affected party as downstream country.
The judgment states
that Networking of Rivers scheme is divided into four major parts:
i) Interlinking of Mahanadi-Godavari-Krishna-Cauvery rivers and building storages at potential sites in these basins.
i) Interlinking of Mahanadi-Godavari-Krishna-Cauvery rivers and building storages at potential sites in these basins.
ii) Interlinking of
West flowing rivers north of Bombay and south of Tapi.
iii) Interlinking of
rivers Ken & Chambal.
iv) Diversion of other
west flowing rivers from Kerala.
It is clear from above
that “Diversion of other west flowing rivers from Kerala” is unlikely to happen
given genuine unanimous opposition from Kerala Assembly.
As to “Interlinking of
Mahanadi-Godavari-Krishna-Cauvery rivers and building storages at potential
sites in these basins”, a recent cover story of Down To Earth underlines the
conflict over water allocation in Mahanadi and Krishna river basin. In Mahanadi
basin, Odisha and Chhattishgarh water is being allocated for industrial use
indiscriminately without accurate forecast of future needs and without any
water sharing treaty. How can water from such a river be diverted for
interlinking of rivers project? In the matter Krishna river basin, there is
already a raging conflict among Maharashtra, Karnataka and Andhra Pradesh
despite adjudication by two Tribunals because demand for water has exceeded
supply ignoring needs for riverine ecology. It has been underlined that ground
water and surface water co-exist but because they have been treated separately
hydraulic connection between the aquifers and the river has been broken is
leading to shrinking of the river because aquifers are not recharging the river
due to overdraft of groundwater. The categorization of Mahanadi as ‘surplus’ a
river is clearly an error of judgment.
At para 62, the judgment reads: “The Court can hardly take unto itself tasks of making of a policy decision or planning for the country or determining economic factors or other crucial aspects like need for acquisition and construction of river linking channels under that program. The Court is not equipped to take such expert decisions and they essentially should be left for the Central Government and the concerned State. Such an attempt by the Court may amount to the Court sitting in judgment over the opinions of the experts in the respective fields, without any tools and expertise at its disposal. The requirements in the present case have different dimensions. The planning, acquisition, financing, pricing, civil construction, environmental issues involved are policy decisions affecting the legislative competence and would squarely fall in the domain of the Government of States and Centre.” But it goes on to add, “We certainly should not be understood to even imply that the proposed projects of inter-linking of rivers should not be completed.”
At para 62, the judgment reads: “The Court can hardly take unto itself tasks of making of a policy decision or planning for the country or determining economic factors or other crucial aspects like need for acquisition and construction of river linking channels under that program. The Court is not equipped to take such expert decisions and they essentially should be left for the Central Government and the concerned State. Such an attempt by the Court may amount to the Court sitting in judgment over the opinions of the experts in the respective fields, without any tools and expertise at its disposal. The requirements in the present case have different dimensions. The planning, acquisition, financing, pricing, civil construction, environmental issues involved are policy decisions affecting the legislative competence and would squarely fall in the domain of the Government of States and Centre.” But it goes on to add, “We certainly should not be understood to even imply that the proposed projects of inter-linking of rivers should not be completed.”
Para 63 of order reads:
“We would recommend, with all the judicial authority at our command, that these
projects are in the national interest, as is the unanimous view of all experts,
most State Governments and particularly, the Central Government. But this Court
may not be a very appropriate forum for planning and implementation of such a
programme having wide national dimensions and ramifications. It will not only
be desirable, but also inevitable that an appropriate body should be created to
plan, construct and implement this inter linking of rivers program for the
benefit of the nation as a whole.” From the above it appears that it is only a
recommendation not an order given the fact that at para 64, it adds, “Realizing
our limitations, we would finally dispose of this Public Interest Litigation”
but goes on to issue sixteen directions including warning for contempt in case
of non-compliance including constitution of a `Special Committee for
Inter-linking of Rivers' with a “liberty to the learned Amicus Curiae to file
contempt petition in this Court, in the event of default or non-compliance of
the directions contained in this order.”
Given the fact that court has recorded its limitations and its jurisdiction, these sixteen directions and warning the states and central agencies of contempt appears to be an act of judiciary overstepping its jurisdiction.
Given the fact that court has recorded its limitations and its jurisdiction, these sixteen directions and warning the states and central agencies of contempt appears to be an act of judiciary overstepping its jurisdiction.
The judgment has failed
to take cognizance of the recommendations of the National Commission for
Integrated Water Resource Development Plan. Volume-I of Commission's report
says: “The Himalayan river linking data is not freely available, but on the
basis of public information, it appears that the Himalayan river linking component
is not feasible for the period of review up to 2050.” It is apparent that ILR
project and Ganga Waterway project pose a threat to Ganga basin. Admittedly, Ganga’s
aviral dhara or unimpded flow and nirmal dhara or quality water flow has
been violated by “dams and barrages that snap her longitudinal connectivity”
and “significant water withdrawals, increased disposal of debris, and altered
water recharge/extraction rates…thereby crippling river functioning.” ILR and
waterway projects entail sever longitudinal connectivity. These projects are contrary
to efforts aimed at rejuvenation of Ganga.
On the Peninsular river
component, the conclusion of this Commission is that "there is no
imperative necessity for massive water transfer. The assessed needs of the
basins could be met from full development and efficient utilisation of
intra-basic resources except in the case of Cauvery and Vaigai basins. Some
water transfer from Godavari towards the south should take care of the deficit
in the Cauvery and Vaigai basins." Here also abundant caution has been
recommended.
It is a sad commentary
on the scientific temper of our policy makers that they have failed to
understand that every river and water source is a living organism (not
mechanically piped water) with different alkalinity acidic and saline levels
that allow for unique and individual ecosystems. Inter-basin transfer and
interlinking of rivers will lead to environmental catastrophe. The fact is that
it a river and land diversion project akin to rewriting of geography. This
implies mindlessly linking toxic river waters with those which are cleaner.
This means mixing glacier waters to grassland waters that will have a killing
effect on the entire ecosystem of the Indian sub-continent. International
rivers like Brahmaputra and Ganga are also involved. It is not surprising these
planners have ended up misleading the Supreme Court in passing the order of
February 27, 2012 on networking rivers in which more than 20 states have shown
no interest it at all and several have explicitly objected to it as is evident
from the order itself.
How Networking of
Rivers Case Started
On 30th September, 2002
the three-judge bench of the then chief Justice, Justice B.N. Kripal, Justice
K.G Balakrishnan, Justice Arijit Pasayat heard the “IN RE: NETWORKING OF
RIVERS” petition and upon hearing the counsel made the following order:
“Learned Amicus Curiae has drawn our attention to Entry 56 List I of the 7th
Schedule to the Constitution of India and contends that the interlinking of the
inter-State rivers can be done by the Parliament and further contends that even
some of the States are now concerned with the phenomena of drought in one part
of the country, while there is flood in other parts and disputes are arising
amongst the (riparian) egalitarian States relating to sharing of water. He
submits that not only these disputes would come to an end but also the
pollution levels in the rivers will be drastically decreased, once there is
sufficient water in different rivers because of their interlinking. Response to
the petition by the Union of India and the States be filed by 28th October,
2002.”
The case was listed for
hearing on 31st October, 2002 and Nikhil Nayyar, Advocate on Record was
appointed as Amicus Curiae to assist Ranjit Kumar, senior advocate appointed as
Amicus Curiae in this matter.
On 31st October 2002,
the petition in question was called on for hearing before the three-judge bench
of Chief Justice BN. Kripal, Justice Y. K. Sabharwal and Justice Arijit
Pasayat. Respondents included Government of India and the State Governments.
Upon hearing counsel the Court made the following order, “Pursuant to the
notice issued by this Court to all the States and the Union Territories in
relation to the inter-linking of the rivers, an affidavit has been filed by the
Union of India and also by the State of Tamil Nadu. No other State or Union
Territory has filed any affidavit and the presumption, therefore, clearly is
that they do not oppose the prayer made in this writ petition and it must be
regarded that there is a consensus amongst all of them that there should be
inter-linking of rivers in India.” A majority of the State governments have yet
to concur with the court’s views. The Kerala assembly has in fact - besides
rejecting the plans for interlinking - questioned the constitutional validity
of transfer of waters from one State to another in its resolution!
The order further says,
“In the counter affidavit filed on behalf of the Union of India, it has, been
stated that the Government of India has been studying and planning for
inter-linking of rivers for over two decades. It is also mentioned in this
affidavit that the Ministry of Water Resources had made a representation on 5th
October 2002 before the Prime Minister on inter-linking of rivers and in that
presentation the Deputy Prime Minister and other senior Ministers and officers
were also present. It was suggested that a High Level Task Force can be formed
which will go into the modalities for bringing consensus among the States. This
affidavit further states that the presentation was also made to the President
of India on 16th October 2002 where emphasis was laid on inter-linking of
rivers that has given rise to the filing of the present petition.”
The order notes, “The Union of India has accepted the concept of inter-linking of rivers and in the affidavit spelt out the benefits. The State of Tamil Nadu is the only State which has responded to the notice issued by this court and filed an affidavit. The said State also supports inter-linking of the rivers and in its affidavit has prayed that a direction be issued on the Union of India for constituting a High Powered Committee in order to see that the project is completed in time schedule. Along with this affidavit the prospective plan for implementation of inter-basin water transfer proposals prepared by the National Water Development Agency in May, 2000 has been placed on record. We are distressed to note that milestone for the perspective plan indicated in the report of the Agency shows that even though the Pre Feasibility Reports regarding the Peninsular & Himalayan projects are already completed, the completion of the link projects ultimately will be completed by the year 2035 in respect of Peninsular Link Project and by 2043 regarding Himalayan Link Project.”
The order notes, “The Union of India has accepted the concept of inter-linking of rivers and in the affidavit spelt out the benefits. The State of Tamil Nadu is the only State which has responded to the notice issued by this court and filed an affidavit. The said State also supports inter-linking of the rivers and in its affidavit has prayed that a direction be issued on the Union of India for constituting a High Powered Committee in order to see that the project is completed in time schedule. Along with this affidavit the prospective plan for implementation of inter-basin water transfer proposals prepared by the National Water Development Agency in May, 2000 has been placed on record. We are distressed to note that milestone for the perspective plan indicated in the report of the Agency shows that even though the Pre Feasibility Reports regarding the Peninsular & Himalayan projects are already completed, the completion of the link projects ultimately will be completed by the year 2035 in respect of Peninsular Link Project and by 2043 regarding Himalayan Link Project.”
After stating this the
order observed, “It is difficult to appreciate that in this country with all
the resources available to it, there will be a further delay of 43 years for
completion of the project to which no States has any objection and whose
necessity and desirability is recognised and acknowledged by the Union of
India. The project will not only give relief to the drought prone areas but
will also be an effective flood control measure and would be a form of water
harvesting which is being rightly propagated by the Union of India and all the
States.” This is quite a weird understanding of water harvesting.
The order further
noted, “Learned Attorney General states that a more realistic view will be
taken and a revised programme on completion would be drawn up and be presented
to the Court. We do expect that the programme when drawn up would try and
ensure that the link projects are completed within a reasonable time of not
more than ten years. We say so because recently the National Highways Projects
have been undertaken and the same is nearing completion and the inter-linking
of the rivers is complimentary to the said Project and the water ways which are
so constructed will be of immense benefit to the country as a whole.” The way
judges considered National Highways Projects for roads as complementary to
networking of rivers provides a glimpse of a flawed reasoning involved.
Misplaced
Claims
In the court at no
stage has the basis of claims of direct benefits from networking rivers, like
the irrigation of 35 million hectares (Mha), full exploitation of existing
irrigation projects of 140 Mha and power generation of 34 million Kilowatt (KW)
mentioned in the February 2012 judgment. Revealing disputable statistics,
National Council for Applied Economic Research (NCAER) study referred to in the
judgment cites different figures. The study states that the ILR programme is
aimed at providing additional irrigation in about 30 million hectares and net
power generation capacity of about 20,000 to 25,000 MW.
The claims of indirect
benefits like flood control, navigation, water supply, fisheries, pollution
control, recreation facilities, employment generation, infrastructure and
socio-economic development etc was also never explained. Only general
statements like “It is emphasized that the cost is negligible when compared to
the potential benefits which may be bestowed on the nation” were made.
The background and
current status of this case is of enormous significance to get a sense of the
world’s biggest river linking project that is pregnant with the possibility of
an ecological catastrophe. The judgment’s Himalayan failure lies in not
recognizing that rivers do change their course and will do so in future as well
because they do not obey judicial command.
The government claims that its engineering exercise will transfer 1500 cubic m of water per second, from the surplus rivers to the Deficit Rivers “through 12,500 km of canals”. On the other hand, official estimate indicate that floodwaters in the Ganga, Brahmaputra, Mahanadi, and the Godavari add up to 30 000 cubic m at peak flow. This mismatch indicates that the inter-linking plan would be totally incapable of solving the annual flood problems in the country.
It is not great jurisprudence to suggest ways of water management without understanding democratic tenets of management through community participation. If there is water problem in various parts of the country, each local region will have its own solution. This strange reasoning of judges to provide judicial solution to management problem defies understanding. Citizens fail to comprehend how it falls under its jurisdiction and mandate of interpretation of law.
The government claims that its engineering exercise will transfer 1500 cubic m of water per second, from the surplus rivers to the Deficit Rivers “through 12,500 km of canals”. On the other hand, official estimate indicate that floodwaters in the Ganga, Brahmaputra, Mahanadi, and the Godavari add up to 30 000 cubic m at peak flow. This mismatch indicates that the inter-linking plan would be totally incapable of solving the annual flood problems in the country.
It is not great jurisprudence to suggest ways of water management without understanding democratic tenets of management through community participation. If there is water problem in various parts of the country, each local region will have its own solution. This strange reasoning of judges to provide judicial solution to management problem defies understanding. Citizens fail to comprehend how it falls under its jurisdiction and mandate of interpretation of law.
The decision making
with regard to ILR entails rewriting the geography of the country.
Selective amnesia of
NCAER Study
Para 31 of the judgment
merits special attention as it takes cognizance of the study that was
undertaken by the National Council for Applied Economic Research (NCAER)
published in April 2008 assessing “the economic impact of the rivers
interlinking program and suggested an investment roll out plan, i.e., a
practical implementation schedule, for the same. A copy of this report was
submitted in the year 2011, before this Court.”
The Foreword to the
NCAER 135 page study claims, “Economic impact of certain benefits such as
mitigation of drought and floods to a certain extent, increased revenue/income
from fishing, picnic site and amusement park are not taken into consideration”
from Interlinking of Rivers. If one looks at NCAER itself observes saying
“interlinking of rivers programme (ILR) programme is aimed at linking different
surplus rivers of country with the deficient rivers so that the excess water
from surplus region could be diverted to deficient region,” it is clear
drought, flood and livelihood from activating like fishing has not been
considered. This is the outcome of the study was meant to assess the macro
impact of the ILR programme on Indian economy both at short- as well as
long-term.
At para 44 of the
judgment, NCAER reference to the recommendations of A Vaidyanathan Committee is
cited but in an exercise of selective amnesia it ignores the fact that
Vaidyanathan has opposed ‘interlinking’ on the grounds of its feasibility,
desirability and viability. Vaidyanathan argues that the volume of flows during
the flood season is misleading as a basis for judging surpluses. Three-fourth
of the water flows in perennial rivers occur between June and September. The
“deficit” regions are far from those considered “surplus” requiring transport
over very difficult terrain and long distances. Moreover, since the surplus
occurs in the rainy season and the demand is in the dry season, it is not
enough to merely carry the water from one point to another. Large storages will
be necessary. One needs to know the quantum of water to be stored, and whether
and where potential sites on the required scale are available, and their likely
impact on environment and human displacement, he says. According to him,
decentralised local rain-water harvesting, by reviving and improving
traditional techniques, can meet essential requirements more effectively and at
a far lesser cost. NCAER’s exercise cannot be termed intellectual honest when
it cites Vaidyanathan’s 2001 paper titled ‘Irrigation Subsidies’ and the 1992
‘Report of the Committee on Pricing of Irrigation Water’ for Planning
Commission under his Chairmanship but his later views that debunk the myth of
‘surplus’ rivers is deliberately ignored.
This is the quality of the NCAER study on the basis of which Ministry of Water Resources claims that the ILR project is viable has revealed that drought and flood is a non-issue as far as economic impact of ILR is concerned. The fact is that the interlocutory application that was filed in the Maili Yamuna case in the Supreme Court was turned into a Public Interest Litigation by the then Chief Justice B N Kripal on the premise that the ILR project would lead to drought proofing and flood proofing of the country. The Court’s order for ILR project was based on the assumption that there is consensus among the states for this project. Subsequently, it has been found that both these premises do not exist.
This is the quality of the NCAER study on the basis of which Ministry of Water Resources claims that the ILR project is viable has revealed that drought and flood is a non-issue as far as economic impact of ILR is concerned. The fact is that the interlocutory application that was filed in the Maili Yamuna case in the Supreme Court was turned into a Public Interest Litigation by the then Chief Justice B N Kripal on the premise that the ILR project would lead to drought proofing and flood proofing of the country. The Court’s order for ILR project was based on the assumption that there is consensus among the states for this project. Subsequently, it has been found that both these premises do not exist.
The NCAER study
observes that the cost of the overall ILR programme was estimated by the task
force/NWDA as Rs 5,60,000 crore at 2002-03 prices. This estimate suffers from
two infirmities. First, the cost of 30 links has been taken, whereas there are
only 29 links. Jogigopa–Tista–Farakka (JTF) is an alternative link to
Manas–Sankosh–Tista–Ganga (MSTG) and only one of these two links will be
constructed. The February 2012 judgment fails to take cognizance of it.
It is noteworthy that
in the meeting of Government’s Experts Committee on Interlinking of Rivers that
Manas and Brahmaputra rivers were discussed. The minutes reveal that it was
contended that they are international in nature, planning of water resources of
the region need lot of care with respect to international dimensions. It has
also been contended that there are problems presently in sharing of Ganga
waters and this type of problem may also arise in Brahmaputra and Manas regions
in additions to the environmental and ecological issues attached to the
regions. Therefore, it is better to give up the MSTG link under ILR.
The NCAER study
considers two alternatives of cost estimates taking into account alternative
links (MSTG or JTF). The new aggregated cost of entire programme with MSTG link
is estimated as Rs 4, 44, 331.20 crore at 2003-04 prices. The new aggregated
cost is Rs 1, 15, 668.20 crore or 20.7 per cent lower than the earlier
aggregate cost estimate of Rs 5,60,000 crore at 2002-03 prices. The new
aggregated cost of entire programme with JTF link is estimated as Rs 4, 34,
657.13 crore at 2003-04 prices. The aggregate cost mentioned in the February
2012 judgment is based on a note by amicus merits further examination. The
judgment did not take note that as per NCAER, the new aggregated cost is Rs 1,
25, 342.87 crore or 22.4 per cent lower than the earlier aggregate cost
estimate of Rs 5, 60, 000 crore at 2002-03 prices.
The study cites experience of Pakistan in the area of interlinking of river could be an inspiration for India arguing that if it can complete the interlinking of its river in 10 years, it should not be difficult for India to complete the task of interlinking of rivers.
The study cites experience of Pakistan in the area of interlinking of river could be an inspiration for India arguing that if it can complete the interlinking of its river in 10 years, it should not be difficult for India to complete the task of interlinking of rivers.
The judgment records at
para 33 that “what happened to the two Action Plan reports submitted by the
Task Force is a matter left to the imagination of anyone” but refrained from
fixing accountability for waste of public money in this regard. After the
change in government and after the winding up of the Task Force, a Special Cell
on interlinking of rivers was created under the Ministry of Water Resources.
Para 39 of the judgment
refers to the NCAER report that underlines the role of the agricultural sector
in higher Gross Domestic Product (GDP) growth. “The report clearly opines that
interlinking of river projects will prove fruitful for the nation as a whole
and would serve a greater purpose by allowing higher returns from the
agricultural sector for the benefit of the entire economy. This would also
result in providing of varied benefits like control of floods, providing water
to drought-prone States, providing water to a larger part of agricultural land
and even power generation. Besides annuring to the benefit of the country, it
will also help the countries like Nepal etc., thus uplifting India's
international role. Importantly, they also point out to a very important facet
of interlinking of rivers, i.e., it may result in reduction of some diseases
due to the supply of safe drinking water and thus serve a greater purpose for
humanity.” It does not explain how it helps Nepal and Bangladesh and how it
will uplift and not undermine India’s international role.
The NCAER study refers
to Tennessee Valley Authority (TVA), Tennessee Valley and Tennessee River in
the USA and efforts at controlling floods, improving navigation, and producing
electrical power and how Damodar valley development project in Jharkhand
emulated facets of the TVA’s development but forgets to mention its
disappointing non-performance. It refers to Indira Gandhi Canal project but
fails to articulate its ecological and human cost. It mentions Colorado River
Canal System in southwest US but ignores how its ecosystem is severely
truncated and degraded by transbasin diversions to advocate ILR project and
still claims to “oversee a water management regime based on a river basin
approach.”
As to mitigation of
flood and drought to a certain extent, fishing at dams and reservoirs, they are
mentioned in passing as “fringe benefit of programme. Thus, all claims of
drought proofing, flood proofing and dilution of pollution through linking rivers
as argued by the lawyer who filed the application 2002 is insincere, an
exercise in sophistry and totally misplaced.
The judgment records
the shortcomings of the NCAER report states as under:
"One shortcoming of the above analysis is that it has not considered the issue of cost of resettlement of displaced people due to ILR Project.”
"One shortcoming of the above analysis is that it has not considered the issue of cost of resettlement of displaced people due to ILR Project.”
Not only that the study
“did not consider the plan's environmental aspects or cost-benefit calculus.” As
per 11th Five Year Plan document, "there are apprehensions that the
assessed surplus is somewhat illusory for many basins and future generations
would actually need all the water." It takes congnisance of
"reservations about the economic viability of such large projects.
Environmental concerns would need to be addressed through the environmental
appraisal process of each project." In such a backdrop, it is indeed
strange that after violating the norms of river basin approach and ecological
integrity of the basin, the judgment records: “NCAER also suggests that after
completion of the linking of rivers programme, the different river links should
be maintained by separate river basin organizations, which would all be
functioning under the direct control of the Central Water Commission or such
other appropriate central body.”
It is a sad commentary
on NCAER’s research that while it acknowledges how agriculture is “susceptible
to the vagaries of rainfall” and the judgment internalizes it in para 46, the
same is not factored in while pronouncing some rivers as surplus and some as
deficit.
All the scholars of law
know that much of English legal thought perhaps being followed by the concerned
judges is obscure, non-scientific, high-minded and not empirical. It is high
time Indian jurists paid heed to analysis in their judgments to banish these
anti-scientific elements from legal thinking in India which has starkly come to
light through this judgment.
Besides technical
problems in the networking of rivers project, given the enormity of political
and legal problems witnessed from the way in which neighboring countries like
Nepal, Bangladesh have raised objections and the way Indian states been
quarrelling with each other over water in general and networking of rivers in
particular, the feasibility of the project is questionable and improbable.
These states have been compelled to flout not only the tribunal awards but also
the apex court orders.
The court has not been
informed about the Report of the National Commission for Integrated Water
Resources Development Plan, Government of India which felt that the
interlinking of Himalayan component may not be feasible till 2050, pondered
over UN Convention on Law of Non-Navigational Uses of International
Watercourses as well. The Report concluded: “The bilateral or regional treaties
and understanding entered by India with any of its neighbors will normally take
precedence over the UN Convention, which is framework to which India is not a
signatory. However, although India abstained from signing the Convention, we
could draw upon the principles enunciated in it usefully for the purpose of
evolving an interpretative matrix not spelt out in our bilateral treaties.”
In the context of
networking of rivers a balance between the theories of limited territorial
integrity and community of interest through a binding international law or
treaty is urgently required to obviate war like situations due to disputes over
sharing of water.
Available Alternative Solution
Available Alternative Solution
In any case the moot
point is how to solve the water problem. As per the Planning Commission’s Tenth
Plan document, there are 383 ongoing major and medium projects awaiting
completion, 111 of which are pending since pre-fifth Plan period i.e. more than
26 years. All these can be completed within five to eight years, yielding an
additional potential of about 14 million hectares at a cost of Rs 77,000 crore
as estimated by the plan task force, now raised to Rs 100,000 crore.
The second component
listed in the Plan is development of minor irrigation, mostly in the eastern
and northeastern regions. The total potential assessed is 24.5 million hectares
with a total investment of Rs 54,000 crore, of which the government is expected
to provide only Rs 13,500 crore, the balance coming from beneficiary farmers
and institutional loans. The cost per hectare is only Rs 20,000 and gestation
period almost nil, against a cost of Rs 100,000 and 12 years' gestation in case
of major and medium projects. The third equally beneficial scheme mentioned in
the Plan is the groundwater recharge master plan prepared by the Central Ground
Water Board needing Rs 24,500 crore to trap 36 billion cubic metres of water
annually.
These measures are
quite clearly better than the project of networking of rivers. The concerned
judges would serve the ecological interest of the subcontinent better if they
could pay heed to these proposals of the Plan document. Judges at all levels
have, by and large, justified the confidence reposed in them. But there is
scope for improvement in several spheres and it is up to the judiciary itself
to rectify the defects in its role and prove to the public that as long as
there is an efficient, impartial, independent and incorruptible judiciary,
democracy in India will be safe from the tyranny of the executive and also the
judiciary.
The apex court came to
the rescue of a river in the Kamalnath motel case where a hotel company which
had stakes of Kamalnath, the then Union Environment Minister (presently Union
Commerce Minister) had unilaterally taken a number of measures to divert the
course of Beas River near Kulu-Manali in Himachal Pradesh (for instance,
earthmovers and bulldozers were used to create a new channel) when floods
threatened land in its possession. The court used the Public Trust Doctrine to
define the state as a trustee of natural resources.
Government’s National
Environmental Policy refers to Public Trust Doctrine saying, “The State is not
an absolute owner, but merely a trustee of all natural resources, which are by
nature meant for public use and enjoyment, subject to reasonable conditions,
necessary to protect the legitimate interest of a large number of people, or
for matters of strategic national interest.”
The NEP says, “The broad direct causes of rivers degradation are, in turn, linked to several policies and regulatory regimes. The result is excessive cultivation of water intensive crops near the headwork’s, which is otherwise inefficient, waterlogging, and alkali-salinization of soil.” It also refers to factors causing reduced flows in the rivers and seeks to ensure maintenance of adequate flows. As an action plan for river systems, the NEP expresses its intent to...“mitigate the impacts on river flora and fauna, and the resulting change in the resource base for livelihoods, of multipurpose river valley projects, power plants, and industries.”
The NEP says, “The broad direct causes of rivers degradation are, in turn, linked to several policies and regulatory regimes. The result is excessive cultivation of water intensive crops near the headwork’s, which is otherwise inefficient, waterlogging, and alkali-salinization of soil.” It also refers to factors causing reduced flows in the rivers and seeks to ensure maintenance of adequate flows. As an action plan for river systems, the NEP expresses its intent to...“mitigate the impacts on river flora and fauna, and the resulting change in the resource base for livelihoods, of multipurpose river valley projects, power plants, and industries.”
The success of a
democracy, especially one based on a federal system, depends largely on an
impartial and independent judiciary endowed with sufficient powers to
administer justice. Judges can import their personal views in interpreting a
statute but they must not assume the role of guardians of public policy and
should not play god. A distinction must be drawn between personal idiosyncrasy
and incorporation of new economic and social policies in the interpretation of
law.
The proposal of
networking peninsular and Himalayan rivers emerges from a lack of rigorous
evaluation of the ecological impacts which would prove disastrous not only to
the fishery, but also to the biodiversity and biotic processes that have
evolved over the past hundred of millions of years. One cannot expect the
judges and legislators to understand but venturing into an area of their
ignorance is against all canons of wisdom.
In the case in question
the judges went on to advise the government that in case consent was not
forthcoming from the states, the government should consider passing a
legislation to obviate consent of the states for this project. Since
criticizing the judges is a criminal offense, the advocates of resistance who
are not shackled by their funding sources from among the citizenry and civil
society need to keep a watch on the impeachable antecedents and future
activities of the judges and legislators because it is quite possible that
legislation for ILR or nationalization of rivers may get introduced in the Parliament.
The rampant violation of the statutory principles and natural justice requires
a vigilant citizens’ network as opposed to fund agency driven initiatives to
investigate as to why the judges and legislators appear to have sold themselves
to the ideology of the free market undermining ecosystem beyond repair and
democratic rights of its citizens to bring the truth about it public domain.
Networking rivers does
not mean drawing some mega litres from one river and pouring it into another
like one does with static containers, or even with canals. The ramifications
are much wider because a river is not only the water that flows or the channel,
which holds the flow rather its much more. The river is the dynamic face of the
landscape. “In the drama of history, the ecosystem is not the stage setting; it
is the cast”.
In the past the court
has rightly and consistently held that large infrastructure projects invariably
raise technical and policy issues which the courts are not equipped to handle.
In view of the reasons cited above and especially an evolving international law
on transboundary rivers there is a clear case for the apex court to review its
order on “networking rivers”.
As per National Water
Policy, 2002, “Water resources development and management will have to be
planned for a hydrological unit such as drainage basin as a whole or for a
sub-basin, multi-sectorally, taking into account surface and ground water for
sustainable use incorporating quantity and quality aspects as well as environmental
considerations.” Outlining India's National Water Policy in 2002, the then
Prime Minister Atal Bihari Vajpayee said that the policy should be
people-centered and those communities ought to be recognized as the “rightful
custodians of water.”This clearly shows that networking of river is contrary to
the Government’s stated policy which means vested interests are so powerful
that they can subvert both executive’s and judiciary’s role.
Given such a background
the judgment in the Writ Petition (Civil) No. 512/2002 is very crucial. In the
days, months and years ahead it is likely to reveal Indian Government’s exact
policy vis-à-vis networking of rivers and court’s considered response while
dealing with contempt applications in the face of sub continental protest. This
case is likely to give birth to a new international legal order to safeguard
the legitimate regime of river basins from the obsolete notions of ‘conquest
over nature’, ‘surplus’ rivers and taming rivers. If the environmental movement
in the Indian sub-continent fails to stop this mega project, it would mean
nothing short of a premature death of the movement itself and acceptance of the
proposed rewriting of sub-continent’s geography with painful consequences as
fait accompli.
In a letter to the
Prime Minister Shri Narendra Modi dated May 21, 2014, ToxicsWatch Alliance
(TWA) had given 15 suggestions one of which argued for abandonment of ILR
project. It drew Prime Minister’s attention towards the pearls of wisdom from Mahabharata that describes the Divine
Being saying, “The mountains are his bones. The earth is his fat and flesh. The
oceans are his blood. Space is his stomach. The Wind is his breath. Fire is his
energy. The rivers are his arteries and veins. Agni and Soma, otherwise called
the Sun and the Moon, are called his eyes. The firmament above is his head. The
earth is his two feet. The cardinal and subsidiary points of the horizon are
his arms,” the new government should reject the idea of “inter-linking of
rivers based on feasibility”. This is narrated by Bhishma in conversation with
Yudhishthira while referring to the reply of sage Bhrigu to sage Bharadwaja.
This verse occurs in the Shanti Parva of
Mahabharata.
TWA had submitted that
interlinking of rivers entails mutilation of the veins and arteries of the
divine nature. Rivers shape the terrain and lives of people by its waters which
are always in a dynamic state. Breaking this dynamic would unleash forces of
uncontrolled change and invite the ‘law of unintended consequences’. Let’s
remember the terrible Aral Sea disaster caused by the mistakes of Soviet Union
in which two Siberian rivers were diverted. If water scarcity is the
perennial question, there better answers like the groundwater recharge master
plan available with the government. Water can be made to “Reach to All Homes,
Farms and Factories” by adopting this plan as well at a minimal cost.
It submitted that
whenever there is conflict between financial gains and rivers, the latter must
get priority over monetary benefits because by any yard stick economic value of
a free flowing river is bigger than dammed and mutilated rivers. The
capitalist, communist and colonial legacy of treating rivers as material flow
that flow through pipelines must be abandoned and rivers must be treated as
living beings that nourished our civilization for centuries and can nourish all
the coming generations if cannibalistic tendency of diverting waters in
bottles, dams and banks is stopped.
With regard to
pollution in rivers, if the Prime Minister can demonstrate the political will
to stop all the effluents and sewage from entering into river streams through a
single executive decision, he would have done an exemplary act of arresting
ecological collapse and for safeguarding the quality of blood flowing in veins
and arteries of the present and future generations. Notably, one of the
aims of the ILR project was dilution of pollution, disregarding its
implications for the clean rivers. NWDA is under structural compulsion to push
these ecologically destructive projects envisaged in 1970s to justify their
continued existence. NCAER, NWDA and their promoters remain trapped in
pre-climate crisis era wherein “taming of rivers”, dams were temples and not outcome
of disease of gigantism and conquest over nature was considered part of
scientific temper with which rivers could be murdered with impunity. The ToRs
of the Task Force of 2002 and 2015 and court orders of 2002 and 2012 reveal
that proponents of ILR project are frozen in a time warp.
For
Details: Gopal Krishna, WaterWatch Campaign, ToxicsWatch
Alliance (TWA). Mb: 08002263335, 09818089660, Email:
gopalkrishna1715@gmail.com, Web:www.toxicswatch.org
Note: WaterWatch
Campaign, ToxicsWatch Alliance (TWA) has been working to highlight the
environmental impact of “networking of rivers” project since November 2002. It
has engaged with concerned Parliamentary Standing Committees, academic
institutions and several peoples’ forum and educational institutions in
Kathmandu and Dhaka. It has organized numerous South Asian conferences on
implications of networking of rivers beginning with the ones at Indian
International Centre, New Delhi in January 2003 and World Social Forum in
Mumbai in 2003. It has engaged in active online, offline and field based
research and advocacy work on water resource issues in Himalayan watershed in
general and Ganga basin in particular. It has been part of several Nadi Yatras (river journeys) between
Bihar and Nepal. It has co-authored books and fact finding reports on Ganga and
Kosi and position papers comparing mega infrastructure projects of South
America and South Asia. It has been part of fact finding research undertaken to
expose transnational companies like Coca Cola. It critiqued UNESCO’s report on
global water. It moderates WaterWatch webgroup with over 3000 members since
March 2003. WaterWatch Campaign has tracked and critiqued the goings on with
regard to networking of rivers. It steers clear of undemocratic groups like
Federation of Indian Chambers of Commerce and Industry (FICCI), Advisory Boards
of corporate conglomerates and banks which hoard black money and promote
ecologically destructive projects. It disapproves of empty corporate social
responsibility initiatives launched with an ulterior motive of brand
positioning. It is the founder member of Ganga Bachao Samiti. It has been
demanding an integrated approach of dealing with land, water and sand besides
virtual water because they co-exist instead of current compartmentalized
approach which is pushing for common and perfect land and water market in
myriad disguises. It has been advocating merger of water quantity and quality and
surface and ground water policy making to avoid parochialism currently being
practiced. It has been demanding legal right for water sources nationally and by
rewriting of UN Convention on Law of Non-Navigational Uses of International
Watercourses. It has been campaigning against bottle water and encroachment of
flood plains. It demands high powered probe into the scam ridden hydro power
sector and farming of water intensive crops in arid areas. It seeks an inquiry
into the link between corporate donations to political parties, NGOs and their
position on water resources projects. It demands a mandatory body burden test
of legislators and judges to ascertain the quantum of hazardous chemicals that
flows in their veins and arteries and their sources. It demands that ministries
of water resources, river development and Ganga rejuvenation, ministry of
environment, forests & climate change, mines and minerals and department of
land development from ministry of rural development be merged and renamed as
natural resources ministry for adoption of a holistic approach. It demands
immediate closure of the mouth the drains that flow into rivers and other water
sources.
Post a Comment